All the following result from quality audits except:
A
Determination of whether project activities comply with organizational policies
B
Improved processes to increase productivity
C
Creation of quality metrics
D
Confirmation of the implementation of approved change requests
Explanation: 

Detailed explanation-1: -1. Which of the following is NOT a part of quality? It’s important for projects to produce a valuable product, but value isn’t really a part of quality. That’s why earned value is part of Cost Management, not Quality Management.

Detailed explanation-2: -The goal of the project quality management should be clearly shared with all stakeholders, and appropriate tasks should be delegated to those responsible. Quality assurance: This involves auditing the quality requirements and quality control results to ensure appropriate quality standards are used.

Detailed explanation-3: -There are three main processes of project quality management. These are Quality Planning, Quality Assurance, and Quality Control.