Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
Deming cycle is also known as
|
PDCA Cycle
|
|
PDCC Cycle
|
|
PPDA Cycle
|
|
None of the above
|
Explanation:
Detailed explanation-1: -The Deming Cycle (or Plan-Do-Check-Act (PDCA)) is a four-step iterative technique used to solve problems and to improve organizational processes. Dr. Walter A. Shewhart, the renowned physicist and statistician from Western Electric and Bell Labs, developed the original concept during the 1920s.