SOFTWARE ENGINEERING

SOFTWARE PROJECT MANAGEMENT

QUALITY MANAGEMENT

Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Following are the actions required when the requirements for products and services are changed. Identify the WRONG statement from the following options.
A
ensure that relevant documented information is amended
B
change of requirements should not be permitted
C
relevant persons are made aware of the changed requirements
D
None of the above
Explanation: 

Detailed explanation-1: -4 Changes to Requirements for Products and Services. You should seek and record evidence that your organization has ensured that all relevant documented information; relating to changed product or service requirements, is amended and those relevant design personnel are made aware of the changed requirements.

Detailed explanation-2: -Six procedure are-Control of Documents, Control of Records, Internal Audit, Corrective Action, Preventive Action, Control of Non Conforming Products.” Six procedure are-Control of Documents, Control of Records, Internal Audit, Corrective Action, Preventive Action, Control of Non Conforming Products.

There is 1 question to complete.