Following are the actions required when the requirements for products and services are changed. Identify the WRONG statement from the following options.
|
ensure that relevant documented information is amended
|
|
change of requirements should not be permitted
|
|
relevant persons are made aware of the changed requirements
|
|
None of the above
|
Explanation:
Detailed explanation-1: -4 Changes to Requirements for Products and Services. You should seek and record evidence that your organization has ensured that all relevant documented information; relating to changed product or service requirements, is amended and those relevant design personnel are made aware of the changed requirements.
Detailed explanation-2: -Six procedure are-Control of Documents, Control of Records, Internal Audit, Corrective Action, Preventive Action, Control of Non Conforming Products.” Six procedure are-Control of Documents, Control of Records, Internal Audit, Corrective Action, Preventive Action, Control of Non Conforming Products.