In ISO 9001:2015 there is no requirement related to Preventive Actions.
|
true
|
|
false
|
|
Either A or B
|
|
None of the above
|
Explanation:
Detailed explanation-1: -In new standards of ISO 9001: 2015 a significant change has been made where term Preventive Action has been dropped not only from the standard but from high level structure as well, means none of the new management system’s standards will have term Preventive Action in the standards.
Detailed explanation-2: -Preventive actions are taken to prevent a potential problem, organizations try to address problems before they happen. Whereas corrective actions are taken after a problem has occurred.
Detailed explanation-3: -ISO 9001:2015 uses the phrase “risk-based approach” instead of “preventive action”.