SOFTWARE PROJECT MANAGEMENT
QUALITY MANAGEMENT
Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
Inputs to control quality include all of the following EXCEPT:
|
Project management plan.
|
|
Quality metrics.
|
|
Work performance data.
|
|
PERT chart.
|
Explanation:
Detailed explanation-1: -What are the 4 stages in the quality assurance process? The 4 stages in the quality assurance process are: Plan, implement, check, and adjust.
Detailed explanation-2: -Quality Management (QM) Quality Assurance (QA) Quality Control (QC)