Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
This concept is a cycle for implementing change which, when followed and repeated, would lead to repeated improvements in the process it was applied to
A
PDCA Cycle
B
PHVA Ciclo
C
Continuous Improvement
D
QMS
Explanation: 

Detailed explanation-1: -The Plan-do-check-act cycle (Figure 1) is a four-step model for carrying out change. Just as a circle has no end, the PDCA cycle should be repeated again and again for continuous improvement. The PDCA cycle is considered a project planning tool.

Detailed explanation-2: -4. Act. The final step involves corrective action and adjustments to implement the improvement project on a larger scale. Since the PDCA Cycle is an iterative loop, the new process becomes a new baseline for future testing.

Detailed explanation-3: -Summary. PDCA or the Deming cycle is a management methodology that aims to continually improve processes. This cycle is based on four stages: plan, do, check, and act. To adapt to market changes, improve efficiency, boost productivity, and meet the needs of your customers, having a method is required.

Detailed explanation-4: -PDCA (Plan-Do-Check-Act) is an iterative, four-stage approach for continually improving processes, products or services, and for resolving problems. It involves systematically testing possible solutions, assessing the results, and implementing the ones that have shown to work.