SOFTWARE ENGINEERING

SOFTWARE PROJECT MANAGEMENT

QUALITY MANAGEMENT

Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Which of the following is the effect of uncertainty and any such uncertainty can have positive or negative effects?
A
Opportunity
B
Event
C
Occurrence
D
Risk
Explanation: 

Detailed explanation-1: -Risk is the effect of uncertainty and any such uncertainty can have positive or negative effects. A positive deviation arising from a risk can provide an opportunity, but not all positive effects of risk result in opportunities.

Detailed explanation-2: -Risk is the Effect of Uncertainty on Objectives. According to ISO 31000, risk is the effect of uncertainty on objectives.

Detailed explanation-3: -A risk is an uncertain event or condition. If it occurs, it will have a positive (good) or negative (bad) effect on the project or a project objective. We call positive risks opportunities and negative risks threats.

There is 1 question to complete.