Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Which one of the following would normal y be considered as one of the ‘costs-of quality’?
A
The Economic Order Quantity
B
Appraisal costs
C
Relocation costs
D
Purchase order discounts
E
Performance-related pay
Explanation: 

Detailed explanation-1: -Common appraisal costs include inspecting materials delivered from suppliers, materials that are a work-in-process or finished goods, supplies used for inspections, and maintenance of test equipment.

Detailed explanation-2: -The four major types of quality costs are prevention, appraisal, internal failure, and external failure.

There is 1 question to complete.