SOFTWARE PROJECT MANAGEMENT
QUALITY MANAGEMENT
Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
Who is ACCOUNTABLE for the Implementation of the Project Quality Plan?
|
Project Director
|
|
Project Manager
|
|
Quality Manager
|
|
CEO
|
Explanation:
Detailed explanation-1: -In general, the project manager has overall responsibility for the quality management process.
Detailed explanation-2: -Role of the project manager The project manager is the individual responsible for delivering the project. The individual leads and manages the project team, with authority and responsibility from the project board, to run the project on a day-to-day basis.
There is 1 question to complete.