Who is ACCOUNTABLE for the Implementation of the Project Quality Plan?
A
Project Director
B
Project Manager
C
Quality Manager
D
CEO
Explanation: 

Detailed explanation-1: -In general, the project manager has overall responsibility for the quality management process.

Detailed explanation-2: -Role of the project manager The project manager is the individual responsible for delivering the project. The individual leads and manages the project team, with authority and responsibility from the project board, to run the project on a day-to-day basis.