SOFTWARE PROJECT MANAGEMENT
RISK MANAGEMENT
Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
|
ALessons learned register
|
|
BProject charter
|
|
CAssumption log
|
|
DRisk report
|
Detailed explanation-1: -The purpose of a risk register in project management is to record the details of all risks that have been identified along with their analysis and plans for how those risks will be treated. Basically, it’s a log that identifies risks along with their severity and the actions and steps to be taken to mitigate the risk.
Detailed explanation-2: -It should include all the identified risks, a description of the risks, how they will impact the project objectives, and the people assigned to manage the risk responses.
Detailed explanation-3: -Step 1: Identify potential risks. Sit down and create a list of every possible risk and opportunity you can think of. Step 2: Determine probability. What are the odds a certain risk will occur? Step 3: Determine Impact. What would happen if each risk occurred? 18-Jun-2022