SOFTWARE PROJECT MANAGEMENT
RISK MANAGEMENT
Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
Question 35 of 100Question ID:613200After losing a member of her high performing team, the project manager implements the response planned for this risk by hiring an independent contractor. However, as a result of adding the new team member, the team is thrown back to the storming stage of team development, and the project falls behind schedule.How might the project manager have avoided this situation?
|
ADeveloped a response plan for the residual risk
|
|
BEstablished sufficient contingency reserves
|
|
CDeveloped a response plan for the secondary risk
|
|
DEstablished sufficient management reserves
|
Explanation:
Detailed explanation-1: -Come up with alternative solutions and path forward just in case the risk happens. Going through alternative solutions while planning makes it easier for the team to adapt to the change because its already been communicated.
Detailed explanation-2: -Identify the risk. Assess the risk. Treat the risk. Monitor and Report on the risk.
Detailed explanation-3: -Generally speaking, projects require five process groups-initiating, planning, executing, monitoring and controlling, and closing. These are known as the PMBOK (Project Management Body of Knowledge) process groups.
There is 1 question to complete.