Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Question 40 of 100Question ID:612442A software development project is running behind schedule because the velocity of the project team has been slowed down by a higher than anticipated complexity of the technology used to develop the product. To bring the project back into alignment with its objectives, the project manager implements the planned response by fast tracking some of the testing activities.What should the project manager do next?
A
AUpdate the schedule using the project management information system (PMIS)
B
BSubmit a change request to update the schedule baseline to reflect the results of fast tracking
C
CSubmit a change request to update the issue log with the final resolution
D
DUpdate the risk register to add the newly identified risk of higher than anticipated complexity
Explanation: 

Detailed explanation-1: -#1: Failing to Properly Define Ideal Users. #2: Time Management Challenges. #3: Understanding the Importance of Testing. #4: Lack of Communication Between Customers and Development Teams. #5: Failing to Find and Retain Skilled Developers for the Project. More items •03-May-2022

Detailed explanation-2: -Organizational (people involved/relationships) Factors. Poor relationships between the project parties. Operational and Technological Factors. Planning and Management Factors. Environmental Factors. Uncertainty Factors. 21-Aug-2021