SOFTWARE ENGINEERING

SOFTWARE PROJECT MANAGEMENT

RISK MANAGEMENT

Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Question 43 of 100Question ID:612658You are a project manager who wants to mitigate the impact of any realized risks for the project. To achieve this goal, you conduct an initial trial at one location before launching to other locations. During the trial, you learn best practices to apply during the national launch and identify pitfalls that should be avoided.Once the trial is over, what should you do with this information?
A
ACapture the information in the lessons learned register
B
BRecord the implementation of the risk responses in the risk register
C
CDocument issues and their resolutions in the lessons learned repository
D
DShare the information with the project sponsor and stakeholders
Explanation: 

Detailed explanation-1: -Through qualitative and quantitative risk analysis, you can determine how the risk is going to impact your schedule and budget. Project management software helps you analyze risk by monitoring your project. ProjectManager takes that one step further with real-time dashboards that display live data.

Detailed explanation-2: -A risk owner is a project manager who is responsible for identifying, assessing, and mitigating risks within a project. Because risks can have a significant impact on the outcome of a project, it’s important for risk owners to have a clear understanding of the potential consequences of each risk.

Detailed explanation-3: -Project risk is a problem that may or may not arise over the course of your project management. There’s no way to control for all potential risks, but thinking through them ahead of time can save your project from failure. It may give a positive or negative effect on the project.

There is 1 question to complete.