SOFTWARE ENGINEERING

SOFTWARE PROJECT MANAGEMENT

RISK MANAGEMENT

Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Question 45 of 100Question ID:613519An infrastructure upgrade project is in the initial planning stage, and the project manager is facilitating a risk workshop focused on prioritizing individual risks for further analysis or action.Which of the following might lead to the development of more effective risk responses for this project?
A
APerforming risk audits
B
BReviewing requirements documentation
C
CMonitoring risks closely
D
DCategorizing risks using RBS
Explanation: 

Detailed explanation-1: -Identify the risk. Assess the risk. Treat the risk. Monitor and Report on the risk. 27-Sept-2021

Detailed explanation-2: -Assume and accept risk. Avoidance of risk. Controlling risk. Transference of risk. Watch and monitor risk. 10-Mar-2023

There is 1 question to complete.