SOFTWARE ENGINEERING

SOFTWARE PROJECT MANAGEMENT

RISK MANAGEMENT

Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Question 55 of 100Question ID:612269During a risk review meeting, the project manager learns that the company has just approved a new policy that prohibits the use of overtime. This restriction represents a new constraint for the project.Where should this newly identified constraint be documented?
A
AThe constraint register
B
BThe risk register
C
CThe assumption log
D
DThe change log
Explanation: 

Detailed explanation-1: -Types of project risks Financial risks such as rising costs, inaccurate budget forecasts, increases in labor and materials, low sales, and challenges in securing funding.

Detailed explanation-2: -Create a project risk register. Identify project risks. Identify opportunities. Determine likelihood and impact. Determine the response. Estimation. Assign owners. Regularly review project risks. More items

There is 1 question to complete.