Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Question 59 of 100Question ID:613608As a project manager, you are leading a project, where you have twelve programmers. Two of them have just handed in their letters of resignation. This realized risk had been identified and accounted for during the planning stage of the project. If no action is taken, you will not meet your deadlines.What should you do next?
A
ACrash the schedule
B
BSubmit a change request to update the schedule baseline
C
CReview the risk register
D
DPerform the Plan Risk Responses process
Explanation: 

Detailed explanation-1: -Step 1: Review the situation. Ensure you have a realistic assessment of the current situation. Step 2: Scope the extent of the problems and be clear on what’s occurring. Step 3: Develop and Implement an action plan. Step 4: Bring in a high performance team. 31-Jul-2018

Detailed explanation-2: -Determine the cause of delays. Revise the shift schedule. Develop a risk management plan. Plan overtime hours. Extend the project deadline. Review your personnel resources. Adjust the project’s parameters. Provide an updated schedule in a common area. More items •26-Jan-2023