Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Question 60 of 100Question ID:613775A previously identified risk has been realized which triggered a risk response. The project team compares the amount of the remaining budget within the cost baseline that was allocated for this risk to the amount of risk remaining in order to determine if the remaining funds are adequate. The result of the project team’s analysis is captured in a burndown chart which will be shared with various project stakeholders.What type of analysis has the project team performed?
A
ASWOT analysis
B
BRegression analysis
C
CContingency analysis
D
DReserve analysis
Explanation: 