Question 65 of 100Question ID:612701An opportunity has triggered some previously approved risk responses. After the primary responses failed to produce the desired results, you discuss fallback plans with your team. The sponsor is concerned and is asking for the current overall risk exposure.What should you do?
A
AConsult the risk management plan
B
BLook in the lessons learned register
C
CRefer the sponsor to the risk register
D
DProvide the sponsor with the risk report
Explanation: 

Detailed explanation-1: -Residual risk is a risk that remains after Risk Management options have been identified and action plans have been implemented.

Detailed explanation-2: -Residual risks are the leftover risks, the minor rin. The PMBOK Guide defines residual risks as “those risks that are expected to remain after the planned response of risk has been taken, as well as those that have been deliberately accepted.”