SOFTWARE ENGINEERING

SOFTWARE PROJECT MANAGEMENT

RISK MANAGEMENT

Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Question 90 of 100Question ID:613645You are preparing to perform multiple iterations of your quantitative cost-schedule risk analysis to evaluate the effects of individual project risks and other uncertainty sources to determine a range of probable outcomes and risks for your project.What analysis type will you use?
A
ADecision tree analysis
B
BAlternatives analysis
C
CMonte Carlo analysis
D
DSensitivity analysis
Explanation: 

Detailed explanation-1: -QTRA is the process of providing numerical estimates of the overall effect of risks on the project objectives when all risks are considered simultaneously. The numerical estimates are usually in terms of schedule and cost.

Detailed explanation-2: -2. Quantitative Risk Assessment. The quantitative risk assessment is used to measure risk by assigning a numerical value. So instead of high, medium, and low, you could have 3, 2 and 1.

Detailed explanation-3: -Quantitative Risk Analysis Formula The industry-standard formula for quantitative risk analysis is: (ALE = SLE × ARO). That is, Annualized Loss Expectancy (ALE) = Single Loss Exposure (SLE) × Annualized Rate of Occurrence (ARO). SLE is calculated as asset value x exposure factor.

There is 1 question to complete.