Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
Which of the following is an output of the Identity Risks process?
|
Activity Duration Estimates
|
|
Scope Baseline
|
|
Risk Register
|
|
Project Schedule Network Diagrams
|
Explanation:
Detailed explanation-1: -The risk register is the output of the identify risks process.
Detailed explanation-2: -The main output from plan risk management is the risk management plan and hence it is also where the remaining five resource management processes are planned.
Detailed explanation-3: -The outputs from risk identification are: risks, triggers, and inputs to other processes. One of the outputs from risk identification is a list of potential project risks.