 Which of the following is an output of the Identity Risks process? 
|  |  Activity Duration Estimates 
 | 
|  |  Scope Baseline 
 | 
|  |  Risk Register 
 | 
|  |  Project Schedule Network Diagrams 
 | 
 Explanation: 
Detailed explanation-1: -The risk register is the output of the identify risks process.
Detailed explanation-2: -The main output from plan risk management is the risk management plan and hence it is also where the remaining five resource management processes are planned.
Detailed explanation-3: -The outputs from risk identification are: risks, triggers, and inputs to other processes. One of the outputs from risk identification is a list of potential project risks.