Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Which of the following is an output of the Identity Risks process?
A
Activity Duration Estimates
B
Scope Baseline
C
Risk Register
D
Project Schedule Network Diagrams
Explanation: 

Detailed explanation-1: -The risk register is the output of the identify risks process.

Detailed explanation-2: -The main output from plan risk management is the risk management plan and hence it is also where the remaining five resource management processes are planned.

Detailed explanation-3: -The outputs from risk identification are: risks, triggers, and inputs to other processes. One of the outputs from risk identification is a list of potential project risks.