SOFTWARE PROJECT MANAGEMENT
RISK MANAGEMENT
Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
Your project has following estimates that 15% probability for $10, 000 profit, 50% probability for $40, 000 profit, and 25% probability for $50, 000 profit. What is the expected profit?
|
$34, 000
|
|
$38, 000
|
|
$42, 000
|
|
$43, 500
|
Explanation:
Detailed explanation-1: -The expected value is defined as the difference between expected profits and expected costs. Expected profit is the probability of receiving a certain profit times the profit, and the expected cost is the probability that a certain cost will be incurred times the cost.
Detailed explanation-2: -Determine the probability (P) an outcome will occur. Determine the monetary value or impact (I) of the outcome. Multiply P x I to calculate the EMV. 21-Jul-2021
There is 1 question to complete.