Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Software testing activities should start
A
As soon as t he code is written
B
During the design stage
C
When the requirements have been formally documented
D
As soon as possible in the development life c ycle
Explanation: 

Detailed explanation-1: -Software testing should start early in the Software Development Life Cycle. This helps to capture and eliminate defects in the early stages of SDLC i.e requirement gathering and design phases. An early start to testing helps to reduce the number of defects and ultimately the rework cost in the end.

Detailed explanation-2: -Stage 5: Testing In this fifth phase of SDLC, the testing is done to ensure that the entire application works according to the customer requirements. After testing, the QA and testing team might find some bugs or defects and communicate the same with the developers.

Detailed explanation-3: -The testing process should begin as soon as the software development lifecycle (SDLC) begins. That means from the very beginning. Testing is finished once the product is no longer supported. OR, a testing cycle is complete once the software is considered stable.

Detailed explanation-4: -Requirements Analysis The first step of STLC is Requirement Analysis. In this stage, testers analyze the software requirements to ensure they are clear, complete, and testable. This is important to ensure that the software is developed according to the specifications.