Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
System integration testing should be done after
A
Integration testing
B
System testing
C
Unit testing
D
Component integration testing
Explanation: 

Detailed explanation-1: -In the end-to-end process of software testing, Integration Testing will be performed after the Unit Testing and before System Testing.

Detailed explanation-2: -On a high level, Unit testing allows us to test a single component of code in isolation which is usually a single method or class. On the other hand, integration testing enables us to test the connection or flow between different components.

Detailed explanation-3: -System Testing Vs System Integration Testing It is conducted after unit testing and will be done each time when a new module is added to the system. It is conducted at the final level i.e. after the completion of integration testing and just before delivering the system for UAT. It is a low-level testing.

Detailed explanation-4: -Unit Testing can be performed at any time, on the other hand, Integration Testing is performed after unit testing and before system testing. Unit Testing is executed by the developer, whereas Integration Testing is performed by the testing team.

There is 1 question to complete.