Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Test plans are not changed or updated once written
A
True
B
False
C
Either A or B
D
None of the above
Explanation: 

Detailed explanation-1: -For example, the test plan is a document that you can write before testing to help your team understand the scope and criteria of the test. During testing, your team may draft a test script and gather test data to evaluate the components outlined in the test plan.

Detailed explanation-2: -Part of test plan: Test plan identifier, Test items, Features to be tested, Features not to be tested, Approach, pass/fail criteria, Testing tasks, Responsibilities, Schedule, Risks and contingencies, Approvals. Therefore, Mission is not part of the test plan.

Detailed explanation-3: -Writing a test plan is typically a test management or leadership responsibility. Others on the test team and in the organization (such as users and developers) may have input and review tasks, but it is generally up to the manager to actually write the test plan.