SOFTWARE ENGINEERING

SOFTWARE TESTING

TEST PLAN AND TEST CASE DEVELOPMENT

Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
This Test Estimation Technique breaks down test project into small pieces
A
Work Breakdown Structure
B
Work-phase based estimation
C
3-Point Software Testing Estimation
D
Functional Point / Testing Point Analysis
Explanation: 

Detailed explanation-1: -The essence of this technique is to divide a complex test project into small components to obtain the following hierarchy: the project is broken down into sub-modules; each sub-module, in turn, is divided into functionalities, which are split into sub-functionalities.

Detailed explanation-2: -1. Top-Down Estimate. Top-down estimates are an estimation technique that starts with an overall time for the project and then breaks that down into phases, which are then broken down further into tasks. This is a classic estimation technique that uses a look such as the work breakdown structure (WBS).

Detailed explanation-3: -Essentially, using a work breakdown structure enables you to take a top-down look at your project and break it into the tasks and subtasks that will get you to completion. It’s a helpful tool that defines a detailed cost or time estimate and provides guidance for schedule development and control.

There is 1 question to complete.