Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
When should you stop testing?
A
when time for testing has run out.
B
when all planned tests have been run
C
when the test completion criteria have been met
D
when no faults have been found by the tests run
Explanation: 

Detailed explanation-1: -1) Stop the testing when the committed / planned testing deadlines are about to expire. 2) Stop the testing when we are not able to detect any more errors even after execution of all the planned test Cases.

Detailed explanation-2: -When Testing should be stopped? d) It depends on risk associated with that project. ANSWER: d) It depends on risk associated with that project. Comment: If the risks associated with the project is high then testing should be done rigorously and it must be effective and efficient.

Detailed explanation-3: -Test Cycle Closure A test closure report by the test lead is published after accomplishing the exit criteria and finishing the testing phase. It follows a standard format such as : Test Summary Report.