SOFTWARE ENGINEERING

SOFTWARE TESTING

TEST PLAN AND TEST CASE DEVELOPMENT

Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Which of the following would NOT normally form part of a test plan?
A
Features to be tested
B
Quality plans
C
Risks
D
Schedules and deadlines
E
Test environment properties
Explanation: 

Detailed explanation-1: -An incident report is used to define the defect of the application. So, incident report is not part of test plan.

Detailed explanation-2: -Explanation: The test plan is a base of every software’s testing. It is a detailed document, which describes software testing areas and activities. It outlines the test strategy, objectives, test schedule, required resources (human resources, software, and hardware), test estimation and test deliverables.

Detailed explanation-3: -Test plan identifier. Unique identifying reference. Introduction. A brief introduction about the project and to the document. Test items. Features to be tested. Features not to be tested. Approach. Item pass/fail criteria. Test deliverables. More items