Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Which set of metrics can be used for monitoring of the test execution?
A
Number of detected defects, testing cost
B
Number of residual defects in the test object
C
Percentage of completed tasks in the preparation of test environment; test cases prepared
D
Number of test cases run / not run; test cases passed / failed
Explanation: 

Detailed explanation-1: -Base Metrics: Analysts collect data throughout the development and execution of test cases to provide base metrics. By generating a project status report, these metrics are sent to test leads and project managers. It is quantified using calculated metrics. The total number of test cases completed.

Detailed explanation-2: -Base Metrics: Base Metrics are the Metrics that are derived from the data gathered by the Test Analyst during the test case development and execution. This data will be tracked throughout the Test Lifecycle.