SOFTWARE TESTING
TESTING PRINCIPLES AND CONCEPTS
|
Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
____ refers to a different set of tasks ensures that the software that has been built is traceable to Customer Requirements
|
|
Validation
|
|
|
Verification
|
|
|
Requirements Engineering
|
|
|
Software Engineering
|
Explanation:
Detailed explanation-1: -Validation refers to a different set of tasks that ensure that the software that has been built is traceable to customer requirements.
Detailed explanation-2: -Verification testing is executed by the Quality assurance team to make sure that the product is developed according to customers’ requirements.
Detailed explanation-3: -The V-model is an SDLC model where execution of processes happens in a sequential manner in a V-shape. It is also known as Verification and Validation model. The V-Model is an extension of the waterfall model and is based on the association of a testing phase for each corresponding development stage.