Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
In risk analysis, what does it mean to calculate the magnitude of a risk?
A
To determine how fast it is.
B
To determine how much it costs.
C
To determine how severe it is.
D
To determine how many risks are available.
Explanation: 

Detailed explanation-1: -Risk = Likelihood x Severity The more likely it is that harm will happen, and the more severe the harm, the higher the risk. And before you can control risk, you need to know what level of risk you are facing. To calculate risk, you simply need to multiply the likelihood by the severity.

Detailed explanation-2: -Calculate the risk of attack: Risk = consequences × likelihood.