REQUIREMENTS ENGINEERING
REQUIREMENTS GATHERING AND ANALYSIS
Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
Process of managing change to requirements
|
Process management
|
|
Requirements management
|
|
Requirements definition
|
|
Requirements discovery
|
Explanation:
Detailed explanation-1: -Setting and documenting current requirements. Clarifying the consequences of the changes. Specifying change control procedure. Creating a project schedule. Communicating with the team. 18-Feb-2022
Detailed explanation-2: -There are four main stages of the requirements management process-planning, development, system verification, and system validation-each with important considerations to the overall project.
Detailed explanation-3: -Change control is the process through which all requests to change the approved baseline of a project, programme or portfolio are captured, evaluated and then approved, rejected or deferred.
There is 1 question to complete.