What is the process of analyzing, documenting, tracking, prioritizing and agreeing on the requirement and controlling the communication to relevant stakeholders?
A
Requirement Management
B
Requirement Elicitation
C
Requirement Analysis
D
Requirement verification
Explanation: 

Detailed explanation-1: -Requirements management is the process of documenting, analyzing, tracing, prioritizing and agreeing on requirements and then controlling change and communicating to relevant stakeholders.

Detailed explanation-2: -The requirements management plan (RMP) describes how the business analysis work will be completed. It describes processes for how requirements will be documented, traced, prioritized, baselined, and changed. We might also think of the RMP as a collection of the plans that are used to manage business analysis.

Detailed explanation-3: -Information requirement analysis (IRA) is an information analysis methodology where the objective is to find the documents needed to carry out a process or an activity in a business model. The methodology is to a great extent inspired from FMEA (Failure Mode and Effect Analysis).