Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
A project manager meets with a customer for initial discussions about an upcoming project. At the end of the meeting, the customer asks the project manager for a rough estimate of the project duration. Based on her experience with three similar projects, the project manager provides an estimate of 8-10 months.What estimation technique does the project manager use?
A
Expert judgment
B
Three-point estimating
C
Analogous estimating
D
Bottom-up estimating
Explanation: 

Detailed explanation-1: -The correct answer is A. The business documents include the business case and the benefits management plan. Both of these documents are created during pre-project work and are available as sources of information about the project’s stakeholders during the first iteration of the Identify Stakeholders process.

Detailed explanation-2: -Which agile ceremony can be incorporated in this project to boost timely cross-functional communication? Daily standups. Daily standups refer to time-boxed meetings of short duration that the project team and relevant stakeholders attend.

Detailed explanation-3: -Which of the following BEST describes the major constraints on a project? Explanation: “Scope, time, cost, quality, risk, resources, and customer satisfaction” is the most accurate list of constraints, or competing demands, that a PM must deal with.