Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
|
a risk metric
|
|
a phase gate
|
|
evidence of a phase completion
|
|
a deliverable
|
|
a proof of concept
|
Detailed explanation-1: -Deliverables and Milestones: A milestone is a significant event or achievement that provides evidence that the deliverable has been completed or that a phase is formally over. While a deliverable includes such things as presentations, report, plans and final application system, a milestone must focus on achievement.
Detailed explanation-2: -Bottom-up estimating involves dividing the project into smaller modules and then directly estimating the time and effort in terms of person-hours, person-weeks, or person-months for each module.
Detailed explanation-3: -The description and scope section of a statement of work would contain statements regarding: project. The highest level of work breakdown structure is the: work breakdown structure.