Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
Estimation of software development effort for organic software is COCOMO is
|
E = 2.4 (KLOC)1.05 PM
|
|
E = 3.4 (KLOC)1.06 PM
|
|
E = 2.0 (KLOC)1.05 PM
|
|
E = 2.4 (KLOC)1.07 PM
|
Explanation:
Detailed explanation-1: -KLOC = The size of the code for the project in Kilo lines of code. a, b = The constant parameters for the software project.
Detailed explanation-2: -COCOMO: It is a procedural cost estimate model for software projects and often used as a process of reliably predicting the various parameters associated with making a project such as size, effort, cost, time, and quality.
There is 1 question to complete.