Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
An estimation technique characterized by the allocation of a timeframe for a specificied activity e.g. a team has two weeks to complete a task and at the end of two weeks work on that task ceases.
|
Guesstimating
|
|
Delphi Technique
|
|
Time Boxing
|
|
Top-Down Estimating
|
|
Bottom-Up Estimating
|
Explanation:
Detailed explanation-1: -Project estimation techniques are tools that help project managers forecast cost, time and other variables as they relate to a forthcoming project. These estimation techniques allow for a more accurate forecast of key elements in every project and include cost, time, scope, risk, resource and quality.
Detailed explanation-2: -Deliverables and Milestones: A milestone is a significant event or achievement that provides evidence that the deliverable has been completed or that a phase is formally over. While a deliverable includes such things as presentations, report, plans and final application system, a milestone must focus on achievement.
There is 1 question to complete.