Function point can be calculated by
|
UFP * CAF
|
|
UFP * FAC
|
|
UFP * Cost
|
|
UFP * Productivity
|
Explanation:
Detailed explanation-1: -CAF = 0.65 + 0.01 N. With this equation, the value of CAF ranges between 0.65 and 1.35. The delivered function points (DFP) are simply computed by multiplying the UFP by CAF.
Detailed explanation-2: -Degree of Influence (DI) for each of these 14 GSCs is assessed on a scale of 0 to 5. The score of all 14 GSCs is totaled to determine Total Degree of Influence (TDI). Then Value Adjustment Factor (VAF) is computed from TDI by using the formula: VAF = (TDI * 0.01) + 0.65.