In COCOMO model, if project size is 300 KLOC, developers have average experience and project schedule is not very tight then which mode is to be selected
A
organic
B
embedded
C
semidetached
D
none of these
Explanation: 

Detailed explanation-1: -Suppose that a project was estimated to be 400 KLOC. Calculate the effort and development time for each of the three modes i.e., organic, semidetached and embedded. E = 3.6(400)1.20 = 4772.81 PM D = 2.5(4772.8)0.32 = 38 PM Page 12 12 Example: 4.6 A project size of 200 KLOC is to be developed.

Detailed explanation-2: -Explanation: Function points and COCOMO are used to evaluate effort.