SOFTWARE PROJECT MANAGEMENT
PROJECT PLANNING AND ESTIMATION
Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
Productivity can be computed by using formula
|
E*D
|
|
E/D
|
|
KLOC/E
|
|
None of these
|
Explanation:
Detailed explanation-1: -P (productivity) = size-effort. P (productivity) = 55, 000-267. P (productivity) = 206 LOC/staff-month. Basic COCOMO offers a way to calculate a set of quick estimates for effort, development time, staffing, and productivity rates, given knowledge only of size and mode.
Detailed explanation-2: -KLOC = The size of the code for the project in Kilo lines of code. a, b = The constant parameters for the software project.
There is 1 question to complete.