Which one of the following is not project attributes?
A
MODP
B
TOOL
C
SCED
D
TURN
Explanation: 

Detailed explanation-1: -Which of the following is NOT a characteristic of a project? Constrained by limited resources Planned, executed, monitored, and controlled Creates a unique product or service Ongoing and repetitive Answer: D Explanation: A project is a temporary endeavor undertaken to create a unique product, service, or result.

Detailed explanation-2: -A project is typically for a customer. The project is temporary in nature. It typically has a defined start and a defined end-point. The project will have a unique set of requirements that need to be delivered within the boundaries of this project.

Detailed explanation-3: -Temporary organization-represents a beginning and an end; Endeavour or production function-represents some actions; and. Objective or outcome-represents something to achieve.