Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
The concept of actors is an integral part of ____
A
Deliverable structure chart
B
Use case diagram
C
Work breakdown structure
D
All of these
E
None of these
Explanation: 

Detailed explanation-1: -A use case diagram mainly consists of actors, use cases and relationships. More complex larger diagrams can include systems and boundaries.

Detailed explanation-2: -How do you create a use case diagram? First, you need to organize your four key elements-system, actors, use cases and relationships. Then, arrange them visually in a way that makes sense and will allow you to see immediately the connections between them.