Typically signing of project charter is the responsibility of
A
Project Sponsor
B
Senior Management
C
Project Manager
D
Project stakeholders
Explanation: 

Detailed explanation-1: -Typically the Project Sponsor approves the charter by signing it (or indicating approval digitally). There may be multiple sponsors, particularly if this is a major project that requires heavy involvement from more than one department.

Detailed explanation-2: -A project charter is typically created near the beginning of a project’s lifecycle and is signed by the sponsor, project manager, and other key stakeholders. The project charter gives the project manager the authority to execute the project and make decisions on behalf of the sponsor.

Detailed explanation-3: -The project charter helps project managers explain to participants and stakeholders the scope of a project, project objectives, who will participate in the project, along with other details such as possible risks.