SOFTWARE PROJECT MANAGEMENT
PROJECT PLANNING AND ESTIMATION
Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
|
True
|
|
False
|
|
Either A or B
|
|
None of the above
|
Detailed explanation-1: -Expert Answer Here, the breaking down of tasks means the project tasks are decomposed into several small tasks to increase productivity. Thus the WBS tool applies decomposition to the tasks and not a composition. Thus option b is not true. WBS structure is carried out as deliverables-based or phases-based.
Detailed explanation-2: -Bottom-up estimating involves dividing the project into smaller modules and then directly estimating the time and effort in terms of person-hours, person-weeks, or person-months for each module.
Detailed explanation-3: -A work breakdown structure is a diagram that shows the connections between the objectives, measurable milestones, and deliverables (also referred to as work packages or tasks).