Which of the following are inputs to the Develop Project Management Plan process?
A
Project charter
B
Enterprise environmental factors
C
Expert Judgment
D
None of the above
Explanation: 

Detailed explanation-1: -Explanation. Inputs to the “Acquire Project Team” process include: Human Resource Management Plan, Enterprise Environmental Factors, and Organizational Process Assets.

Detailed explanation-2: -Of the choices, the project scope statement is the only input to the project plan development.

Detailed explanation-3: -Enterprise Environment Factors (EEFs) include all policies, practices, procedures, and legislation that exist both inside and outside of the organization that will impact the way you manage a project.

Detailed explanation-4: -The enterprise environmental factors that may be updated as a result of the Develop Project Team process include, but are not limited to, personnel administration, employee training records, and skill assessments.