SOFTWARE PROJECT MANAGEMENT
PROJECT PLANNING AND ESTIMATION
Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
|
Policies
|
|
Procedures
|
|
Government Regulation
|
|
Lessons learned
|
Detailed explanation-1: -Infrastructure is not considered an organizational process asset. The PMI considers the infrastructure to be an enterprise environmental factor that is outside the control of the project team.
Detailed explanation-2: -Common examples of processes include new product development, order fulfillment, and customer service; less obvious but equally legitimate candidates are resource allocation and decision making.
Detailed explanation-3: -Which of the following is NOT an organizational process asset that might influence this process? A scheduling software tool is an element of project management information system, which is defined as an enterprise environmental factor, rather than an organizational process asset.