Which of the following is not an example of Organizational Process Assets?
A
Policies
B
Procedures
C
Government Regulation
D
Lessons learned
Explanation: 

Detailed explanation-1: -Infrastructure is not considered an organizational process asset. The PMI considers the infrastructure to be an enterprise environmental factor that is outside the control of the project team.

Detailed explanation-2: -Common examples of processes include new product development, order fulfillment, and customer service; less obvious but equally legitimate candidates are resource allocation and decision making.

Detailed explanation-3: -Which of the following is NOT an organizational process asset that might influence this process? A scheduling software tool is an element of project management information system, which is defined as an enterprise environmental factor, rather than an organizational process asset.