SOFTWARE PROJECT MANAGEMENT
PROJECT SCHEDULING AND TRACKING
| 
 Question 
 [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
 
 | 
 A key input to the Define Activities process is the- 
| 
 | 
  Project management plan 
 
 | 
| 
 | 
  Project scope statement 
 
 | 
| 
 | 
  Project scope baseline 
 
 | 
| 
 | 
  Project charter 
 
 | 
 Explanation: 
Detailed explanation-1: -Inputs to the Define Activities process are: Schedule management plan, work breakdown structure, project schedule, and network diagram.
Detailed explanation-2: -According to the PMP Training, Define Activities is the process of identifying and documenting the specific actions to be performed to produce the project deliverables.
Detailed explanation-3: -inputs to the Define Activities process are. schedule management plan, scope baseline, enterprise environmental factors, and organizational process assets.
 There is 1 question to complete.