Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
A key input to the Define Activities process is the-
A
Project management plan
B
Project scope statement
C
Project scope baseline
D
Project charter
Explanation: 

Detailed explanation-1: -Inputs to the Define Activities process are: Schedule management plan, work breakdown structure, project schedule, and network diagram.

Detailed explanation-2: -According to the PMP Training, Define Activities is the process of identifying and documenting the specific actions to be performed to produce the project deliverables.

Detailed explanation-3: -inputs to the Define Activities process are. schedule management plan, scope baseline, enterprise environmental factors, and organizational process assets.