SOFTWARE PROJECT MANAGEMENT
PROJECT SCHEDULING AND TRACKING
Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
A key input to the Define Activities process is the-
|
Project management plan
|
|
Project scope statement
|
|
Project scope baseline
|
|
Project charter
|
Explanation:
Detailed explanation-1: -Inputs to the Define Activities process are: Schedule management plan, work breakdown structure, project schedule, and network diagram.
Detailed explanation-2: -According to the PMP Training, Define Activities is the process of identifying and documenting the specific actions to be performed to produce the project deliverables.
Detailed explanation-3: -inputs to the Define Activities process are. schedule management plan, scope baseline, enterprise environmental factors, and organizational process assets.
There is 1 question to complete.