SOFTWARE PROJECT MANAGEMENT
PROJECT SCHEDULING AND TRACKING
Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
|
. Limed value analysis
|
|
Schedule change control system
|
|
Trend analysis
|
|
Reserves
|
Detailed explanation-1: -Answer: D (Reserves) The project manager needs to reserve the employees based upon the activity duration given by his team for developing the scheduling process as i…
Detailed explanation-2: -Project estimation is the process of forecasting the time, cost, and resources needed to deliver a project. It typically happens during project initiation and/or planning and takes the project’s scope, deadlines, and potential risks into account.
Detailed explanation-3: -This is a process where you look at each individual activity and determine what and how many resources are needed to accomplish that activity. Resources are not just people, but also include equipment, machines, and different types of supplies needed to finish the activity.