Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
Working with your team to provide the basis for measuring and reporting schedule progress, you agree to consider the-
|
Schedule data
|
|
Network diagram
|
|
Schedule baseline
|
|
Technical baseline
|
Explanation: