Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
A project manager is informed midway through project planning that she was given inaccurate data regarding new regulations affecting the required end date of her project. She may need to make a few adjustments, but she thinks she can still manage the project to complete it before the regulations take effect. She confirms this by analyzing the sequence of activities with the least amount of scheduling flexibility. What technique is she using?
|
Critical path method
|
|
Flowchart
|
|
Precedence diagramming
|
|
Work breakdown structure 1. A project manager is informed midway through project planning that she was given inaccurate data regarding new regulations affecting the required end date of her project. She may need to make a few adjustments, but she thinks she can still manage the project to complete it before the regulations take effect. She confirms this by analyzing the sequence of activities with the least amount of scheduling flexibility. What technique is she using? Work breakdown structure Precedence diagramming Flowchart Critical path method
|
Explanation:
Detailed explanation-1: -A baseline in project management is a clearly defined starting point for your project plan. It is a fixed reference point to measure and compare your project’s progress against. This allows you to assess the performance of your project over time.
Detailed explanation-2: -Expert judgment is often used to analyze the information needed to decompose the project deliverables down into smaller component parts in order to create an effective WBS.