Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Project schedule development is an iterative process. If the start and finish dates are not realistic, the project probably will not finish as planned. You are working with your team to define how to monitor any schedule changes. You documented your decisions in which of the following?
A
Schedule change control procedures
B
Schedule management plan
C
Schedule risk plan
D
Service-level agreement
Explanation: 

Detailed explanation-1: -Closure or Termination Once you have reached your goals and the project deliverables have been signed off on by all the stakeholders involved, it is time for the closing or termination phase of the project. During this phase, you must hand off the deliverables to the client.

Detailed explanation-2: -Change control is a methodology used to manage any change requests that impact the baseline of your project.